Our label kits have been designed for Franklin BESS with following scenario:

  • FranklinWH BESS
  • Solar inverter labels not included in this label kit
  • 1 aGate
  • Up to 2 aPower batteries
  • Generator installed or no generator installed
  • With partial backup
  • Whole house backup
  • Main metering panel is the same location as MSB
  • Battery system location is not hard to find, or in a large building.


If your installation falls outside this scenario, additional labels will be required.

  • DC and AC cables not in the same wiring enclosure without an insulating barrier (conduit)
  • Not installed in a BESS room, or BESS room only has 1 door.
  • Not designed for non-backup
  • Not designed for solar only (must have battery)
  • MSB connected aGate directly, no other switchboard
  • Inverter adjacent to switchboard or not. 
  • No 3rd party batteries. 
  • No EV connected.
  • No IPSD