PowerPlus Label Kit installation Diagram

Single Phase BESS with Backup


Three Phase BESS With Backup


Rooftop


Individual Label Location Breakdown


Label

Instruction

1

To be installed adjacent to battery enclosure or on all doors to the room where the battery is located.

 

 

 

 

 

 

 

2

To be installed adjacent to battery enclosure or on all doors to the room where the battery is located.

Current and Voltage values to be filled out according to site specifics.

 

3

To be installed adjacent to the PowerPlus battery and adjacent to the equipment to be operated in event of a shutdown (usually the switchboard the battery/inverter is connected to).

 

4

To be installed below each shutdown procedure label.

5

Where both solar and a battery is installed, this label is to be installed adjacent to the inverters.

6

To be installed on the white space on the bottom left hand side of the plaque (if you wish), or any other location you prefer. Not a required label so can be omitted. Engrave details as you wish or stick your own logo/sticker on top.

7

These labels shall be installed adjacent to each PowerPlus Whispr inverter. Label kit includes suitable labels if 3 battery systems are installed, if there are more, additional labels need to be sourced.

8

 

 

 

To be installed adjacent to each DC Switch (top right side as per shutdown procedure) on the Whisper inverter. Label kit includes suitable labels if 3 battery systems are installed, if there are more, additional labels need to be sourced.

9

 

 

 

When more than 1 battery system (stacks of batteries) is installed, these labels shall be installed adjacent to each PowerPlus battery/inverter. Label kit includes suitable labels if 3 battery systems are installed, if there are more, additional labels need to be sourced. When only 1 battery system is installed, neither of these labels is required.

10

 

 

To be installed adjacent to each backup isolator (at right side panel as per shutdown procedure) on the Whispr inverter. Label kit includes suitable labels if 3 battery systems are installed, if there are more, additional labels need to be sourced.

11

 

                     

 

To be installed adjacent to each grid isolator (at right side panel as per shutdown procedure) on the Whispr inverter. Label kit includes suitable labels if 3 battery systems are installed, if there are more, additional labels need to be sourced.

12

 

 

 

To be installed adjacent to each grid isolator (at left side panel as per shutdown procedure) on the Whispr inverter. Label kit includes suitable labels if 3 battery systems are installed, if there are more, additional labels need to be sourced.

13

When more than 1 battery system (stacks of batteries) is installed, this label is required to be installed adjacent to 1 of the inverters. Not required when only one battery system is installed.

14

 

 

To be installed to the switchboard where the system is configured for whole home backup, or where all load circuits within the distribution board or switchboard are backed up.

15

 

 

To be installed adjacent to the main isolator in the essential loads.

16

 

 

To be installed adjacent to each backed-up circuit. Label kit includes suitable labels for 17 backed-up circuits, if there are more, additional labels need to be sourced.

17

 

  

 

To be installed adjacent to each switch that the Whispr inverter backup port are connected to.

18

 

                                                        

 

To be installed adjacent to each switch that the Whispr inverter grid port are connected to.

 

19

            

To be installed adjacent to each switch that the Whispr inverter grid port are connected to. Not required when two inverters are installed.

20

 

To be installed adjacent to the changeover switch to match the corresponding position.

21

 

To be installed adjacent to the changeover switch to match the corresponding position.

22

 

 

To be installed adjacent to the changeover switch.

23

 

To be installed adjacent to the main isolator for the non-backup loads. If there is no main isolator for these loads (or there is no non-backup loads), this label is not required.

24

 

 

To be installed adjacent to the switch the PowerPlus smart energy meter is connected to. If PowerPlus smart energy meter has not installed, this label is not required.

25

To be installed adjacent to the PowerPlus smart energy meter. If PowerPlus smart energy meter has not installed, this label is not required.

26

To be installed adjacent to the main switch on the MSB.

27

To be installed adjacent to the hot water main switch on the MSB.

28

To be installed on the switchboard which the PowerPlus Whispr inverter is directly connected to.

29

 

 

To be installed on MSB and all distribution switchboards electrically connected between the MSB and the switchboards to which the PowerPlus Whispr inverter is directly connected. 1 label is provided in our kits, so if the PowerPlus Whispr inverter is connected to a switchboard other than the MSB, additional labels need to be sourced.

30

To be installed on the MSB. Only required in Victoria.

31

To be installed on MSB and main metering panel. Label kit includes 1 label assuming the meter panel is the same location as the MSB, if this is not the case an additional label is required. Install the “SW” label on top of the “DP” where rooftop DC isolators are used instead of disconnection points.

32

To be installed on MSB and main metering panel. Label kit includes 1 label assuming the meter panel is the same location as the MSB, if this is not the case an additional label is required.

33

To be installed on MSB or meter box and Fire panel.

 

Roof Section                                                                      

34

Where DC cabling is installed within a ceiling space, this label is to be installed adjacent to the access point into the ceiling.

 

35

To be installed adjacent on each DC isolator (not required if disconnection points are used instead of rooftop isolators).

36

 

To be attached to the PV module or structure within 300mm of all disconnection points (not required if rooftop isolators are used instead of disconnection points).

37

 

To be attached (typically zip tied) to positive and negative cables of all disconnection points (not required if rooftop isolators are used instead of disconnection points).

 

Labels required for all installations, which are not included in our kit.

 

To be attached on DC cabling from the array to the inverter at intervals not less than 2m and at every change of direction. These labels are not included in the label kit and must be sourced separately.

To be installed on MSB and fire panel shown on a plan (Map or drawing) when the battery system locations that are difficult to find or where the inverter (IES) is not within 3 meters and fully visible from the switchboard. This sign must indicate location of shutdown procedure and inverter. This label does not include in the label kit and must be sourced separately.