Does this change for 1PH, 2PH and 3PH sites?

Avatar
Discard
Author

When using the Single phase or 3 phase M-Combiner backup gateways the max is 6 batteries per site.
If backup is not required a M-Gateway monitoring EMS system can support up to 18 batteries.

Avatar
Discard

Your Answer

Please try to give a substantial answer. If you wanted to comment on the question or answer, just use the commenting tool. Please remember that you can always revise your answers - no need to answer the same question twice. Also, please don't forget to vote - it really helps to select the best questions and answers!

Related Posts Replies Views Activity
1
Mar 26
524
1
Mar 26
586
1
Mar 26
594
1
Apr 26
446
1
Apr 26
469